Mumbai ,01.10.2019 : HPCL’s Visakh-Vijayawada-Secunderabad-Pipeline (VVSPL) Capacity Expansion Project has been commissioned ahead of schedule and put into operation smoothly. The Project has enhanced VVSPL capacity from 5.38 MMTPA to full design capacity of 7.7 MMTPA.

As part of the project, 13 new pumps have been installed: 3 each at the 2 new Intermediate Pump Stations (IPS) viz. M B Patnam IPS and J K Gudem IPS, 2 at the new Bogaram IPS, 1 each at the existing Pump Stations of Visakhapatnam, Rajahmundry, Vijayawada and 2 at Suryapet.

In addition to above, OSTT-SS Jetty Sub-Sea Pipeline has also been mechanically completed.

It is pertinent to mention here that all project sites have reported impeccable safety record with NIL incidents and ZERO man-hour loss.

Related posts

IIUSA in association with PHD Chamber of Commerce and Industry Commences India EB-5 Passport Roadshow Series

EV Market In India Likely To Be A USD206 Billion Opportunity By 2030

mumbainewsexpress

Beauty Garage Professional records a 60% yearly growth, expanding its market share in the hair care and treatment segment through a diverse product range

Leave a Comment

23 − = 13